Milestones List
Project Presentation
Project Deliverables
Annual Public Reports

 

Milestones List

number
month
date
description
1
6
November 2002

Specifications of requirements.
Project Management Plan.
Finalised conceptual phase, with detailed industrial requirement specifications, and metrics for measuring the actual benefits from the results versus the measurable project objectives.

2
18
November 2003

Completion of specifications of all components and producing early prototypes.
Early prototype developed, at which point the expected achievements of the system can be estimated.

3
27
August 2004

Early assessment of the system performed.
AIM components have been implemented and are integrated.

4
36
May 2005
Full system training completed and as a result the system is fully validated against the requirements and the project objectives.

 

Project Presentation

to top
description

Project Presentation: Brochure with the main objectives and achievements of AIM.

 

Project Deliverables

to top
description

D2.1.2: Specification for collection system

D2.2.2: Specification of innovation engine

D2.3.2: Specification of innovation repository

D3.1.2: Innovation Viability Assessment Specification

D3.2.2: Innovation Management System Specification

D3.3.1: Specification of WEB infrastructure

D4.3/D4.4: Summary of WEB infrastructure Implementation and Integrated System

 

Annual Public Reports

to top
description

Annual Public Report N°1, Covering period 1.6.2002 - 31.05.2003

Annual Public Report N°2, Covering period 1.6.2003 - 31.05.2004

Final public report, Covering period 1.6.2002 - 30.09.2005

 

to top